April 2, 2013 (SolarReserve)
“SolarReserve, a U.S. developer of large-scale solar power projects…announced completion of the assembly of the molten salt receiver panels that sits on top of the 540 foot solar power tower for its 110 megawatt (MW) Crescent Dunes Solar Energy Plant located near Tonopah, Nev…[T]he Crescent Dunes Plant will be the nation’s first commercial-scale solar power tower facility with energy storage and the largest power plant of its kind in the world… “The project will utilize technology developed in the U.S. by SolarReserve and its technology partners to capture and store the sun’s energy in order to deliver a firm electricity supply to Nevada, day or night, without the need to burn fossil fuels. The molten salt ‘receiver’ is actually comprised of panels formed by hundreds of special alloy tubes which will be flowing with molten salt for energy absorption and storage…[T]he project will be capable of storing 10 hours of full load electricity production, enough to power 75,000 homes at peak electric demand periods, even after dark.”
“The project closed financing and initiated construction in September of 2011 and is scheduled to complete construction and start plant commissioning at the end of 2013, including first electricity production by the end of the year. The Crescent Dunes project has secured a 25-year power purchase agreement with NV Energy to sell 100 percent of the electricity output…[It] is jointly owned by SolarReserve, ACS Cobra Group, a worldwide leader in the engineering and construction of power plants and thermal solar facilities, and Santander Group, a global financial services and banking leader. ACS Cobra’s Nevada-based affiliate, Cobra Thermosolar Plants Inc., is the general contractor… “Construction is expected to peak at more than 600 jobs on site during the 30-month construction period and is estimated to create more than 4,300 direct, indirect and induced jobs at companies throughout the U.S. that provide engineering, equipment supply and manufacturing, transportation and other value-added services. To date, orders for the project have been placed for equipment and services in more than 21 states. Once operational, the project will expend more than $10 million per year in salaries and operating costs, and is forecasted to generate $73 million in total tax revenues through the first 20 years of operation…”
0 comments:
Post a Comment